Construction Info
- Concrete belt foundation, concrete belt + "Colombia" concrete block 240 mm
- Exterior wall: Fibo5 thickness 200 mm + Insulation EPS 200 mm
- Concrete floor slabs
- Inner walls: Gypsum board with metal frame, FIBO on the first floor
- Roof: Flat roof, SBS roofing material with insulation, OSB panel
- Facade: partially rendered panels
- Windows: PVC plastic windows with triple glazing
- Terraces and Balcony doors: 1st floor – Wooden door with triple glazing parallel sliding door, 1st floor - PVC balcony door
- Front entrance door: Wooden
- Interior doors: hollow-core flush doors
Technical systems
- Heating: Each boiler has its own air-water heat pump NIBE COP 4.6 Boiler - 200 l
- The air-water heat pump boiler also heats utility water
- The first and second floors have floor water heating
- Electricity - 3x 20A, double tariff meter, main electrical panel, wiring is prepared for easy TV connection, protection and fire alarms.
- Centralized water supply and sewer drainage system
- Land drainage
- Internet - Starman
- Energy grading class - B
- Ventilation - heat recovery ventilation unit
- Boxes No 2 and 5 have solar panels